OK there's an update on how things stand at the end of play on the 31Aug18.
Hwyl
Penri
- The pipework behind the Wendy House to the Wendy Street stage barrels and Hanham building MDPE (blue) pipes is complete with a temporary link around where the pump will be (see photographs attached).
- Holes have been drilled in the top of the Wendy Street stage barrels; filter material has been procured, cut and fitted; and the down pipe feed from the stage gutter cut and diverted to suit (all we need now is some rain to see if it all works as planned).
- A design for a bracket to hold the linear actuator and gate valve has been produced and is out with a fabricator for estimating.
- A design for a coupling between the linear actuator and the gate valve has been produced and 3D printed samples manufactured for trial purposes.
- Plumbers Mait has been applied to the piping connecting to the 3D printed join behind the Wendy house, this join needs monitoring.
Hwyl
Penri
- Attachments
-
- IMG_2323.jpg (3.03 MiB) Viewed 790 times
Re: Spring / Summer April 2018 and onwards deployment(s)
... further photos.
- Attachments
-
- IMG_2324 5.jpg (3.9 MiB) Viewed 789 times
Re: Spring / Summer April 2018 and onwards deployment(s)
... and the last one
- Attachments
-
- IMG_2325 5.jpg (3.2 MiB) Viewed 789 times