Page 1 of 1
Preliminary activity
Posted: 15/03/2020, 21:38
by Penri
These posts cover the initial work being done to provide a 12V dc infrastructure to WMT model buildings.
Details will be added and updated as they become available.
Re: Preliminary activity
Posted: 28/03/2020, 13:46
by Penri
Attached are two photographs relating to the WMT building lighting activity
One shows the 12V distribution box located next to the fence near the WMT Wesleyan Chapel. This photograph was taken before the cables were routed via the underground ducts to the various points of need.
- IMG_4782.jpeg (597.41 KiB) Viewed 879 times
The other is of the PSU, Voltmater/Ammeter and fused distribution assembly all mounted on a plywood base ready for insertion into the box. The photographs also shown 2off 12V 10W flood lights being used as loads for test purposes.
- IMG_4871.jpeg (400.49 KiB) Viewed 879 times
Re: Preliminary activity
Posted: 28/03/2020, 22:41
by Penri
Update description document.
Re: Preliminary activity
Posted: 19/06/2020, 12:22
by Penri
Progress since last posting.
Distribution board installed in box:
- IMG_4934.jpeg (1.95 MiB) Viewed 825 times
Wesleyan Chapel wired in:
- HDR Front 2_DxOVP.jpeg (138.48 KiB) Viewed 825 times
more information to follow on lighting in Chapel
... and Ian as complete re-lighting and re-wiring all the dioramas, example of how work:
- IMG_5312.jpeg (2.54 MiB) Viewed 825 times
... he even drilled up through the candlestick to insert a seriously small led! I think it looks fabulous.
More soon.